Specificaton
Project ID | : | 42 |
Project Title | : | Installation of Solar Powered Plant at Army Headquarters and all Formation Headquarters to Mitigate Low Carbon Emission and Development of Renewable Energy (T5P4) |
Project Category | : | |
Fund & Cost
Total Estimated Cost | : | 1200 |
Total Fund Released | : | 1199.9 |
Percentage of Fund Released | : | 1.00 % |
Progress
Date of Financial Progress | : | 30/09/2015 |
Date of Physical Progress | : | 31/10/2015 |
Cumulative Financial Progress | : | 558.45294 |
Percentage of Financial Progress Against Total Fund Released | : | 0.47 |
Percentage of Financial Progress Against Total Estimated Cost | : | 0.47 |
Percentage of Physical Progress | : | 0.78 |
Comments
Comments of Last Fields | : | |