Implementation Progress Details

Specificaton

Project ID : 435
Project Title : সুন্দরবন সংরক্ষিত বনে এসএমএআরটি পেট্রোলিং
Project Category :

Fund & Cost

Total Estimated Cost : 210
Total Fund Released : 52.5
Percentage of Fund Released : 0.25 %

Progress

Date of Financial Progress :
Date of Physical Progress : 28/02/2019
Cumulative Financial Progress : 52.5
Percentage of Financial Progress Against Total Fund Released : 1.00
Percentage of Financial Progress Against Total Estimated Cost : 0.25
Percentage of Physical Progress : 0.60

Comments

Comments of Last Fields :