Specificaton
Project ID | : | 440 |
Project Title | : | Climate change adaptation to protect Human Health in Bhawanigonj pourosova under Rajshahi District |
Project Category | : | |
Fund & Cost
Total Estimated Cost | : | 200 |
Total Fund Released | : | 100 |
Percentage of Fund Released | : | 0.50 % |
Progress
Date of Financial Progress | : | 23/06/2019 |
Date of Physical Progress | : | 25/09/2019 |
Cumulative Financial Progress | : | 100 |
Percentage of Financial Progress Against Total Fund Released | : | 1.00 |
Percentage of Financial Progress Against Total Estimated Cost | : | 0.50 |
Percentage of Physical Progress | : | 0.80 |
Comments
Comments of Last Fields | : | |