Project ID | : | 47 |
Project Title | : | Re-excavation of Drainage Khal of Madaripur Beel Route Chabnnel (MBR) of Gopalgonj District due to Climate Change Under Climate Change Turst Fund |
Project Category | : | |
Fund & Cost
Total Estimated Cost | : | 502.37 |
Total Fund Released | : | 291.6 |
Percentage of Fund Released | : | 0.58 % |
Progress
Date of Financial Progress | : | 27/10/2013 |
Date of Physical Progress | : | |
Cumulative Financial Progress | : | 284.14 |
Percentage of Financial Progress Against Total Fund Released | : | 0.97 |
Percentage of Financial Progress Against Total Estimated Cost | : | 0.57 |
Percentage of Physical Progress | : | 1.00 |
Comments
Comments of Last Fields | : | |