Specificaton
Project ID | : | 533 |
Project Title | : | উপকূলীয় চরফ্যাশন উপজেলায় ঘুর্ণিঝড় সহিষ্ণু আশ্রয় কেন্দ্র-কাম-ডাক বাংলো নির্মাণ |
Project Category | : | |
Fund & Cost
Total Estimated Cost | : | 499.18 |
Total Fund Released | : | 374.385 |
Percentage of Fund Released | : | 0.75 % |
Progress
Date of Financial Progress | : | |
Date of Physical Progress | : | 30/11/2020 |
Cumulative Financial Progress | : | 249.14 |
Percentage of Financial Progress Against Total Fund Released | : | 0.67 |
Percentage of Financial Progress Against Total Estimated Cost | : | 0.50 |
Percentage of Physical Progress | : | 0.80 |
Comments
Comments of Last Fields | : | |