Specificaton
Project ID | : | 58 |
Project Title | : | Electrification in local area (Upazila Complex) by using Solar Energy |
Project Category | : | |
Fund & Cost
Total Estimated Cost | : | 2460.8 |
Total Fund Released | : | 1363.612 |
Percentage of Fund Released | : | 0.55 % |
Progress
Date of Financial Progress | : | 30/06/2014 |
Date of Physical Progress | : | 30/06/2014 |
Cumulative Financial Progress | : | 833.412 |
Percentage of Financial Progress Against Total Fund Released | : | 0.61 |
Percentage of Financial Progress Against Total Estimated Cost | : | 0.34 |
Percentage of Physical Progress | : | 1.00 |
Comments
Comments of Last Fields | : | |