Implementation Progress Details

Specificaton

Project ID : 619
Project Title : কসবা পৌরসভায় ড্রেনেজ অবকাঠামো উন্নয়ন
Project Category :

Fund & Cost

Total Estimated Cost : 233
Total Fund Released : 116.5
Percentage of Fund Released : 0.50 %

Progress

Date of Financial Progress :
Date of Physical Progress :
Cumulative Financial Progress :
Percentage of Financial Progress Against Total Fund Released :
Percentage of Financial Progress Against Total Estimated Cost :
Percentage of Physical Progress : 1.00

Comments

Comments of Last Fields :