Implementation Progress Details

Specificaton

Project ID : 86
Project Title : Structural development to cope with the adverse impacts of climate change in Pangsa Pourashava
Project Category :

Fund & Cost

Total Estimated Cost : 195.85
Total Fund Released : 147.0375
Percentage of Fund Released : 0.75 %

Progress

Date of Financial Progress : 31/08/2014
Date of Physical Progress : 19/04/2016
Cumulative Financial Progress : 147.0375
Percentage of Financial Progress Against Total Fund Released : 1.00
Percentage of Financial Progress Against Total Estimated Cost : 0.75
Percentage of Physical Progress : 1.00

Comments

Comments of Last Fields :