Project ID | : | 98 |
Project Title | : | Protection of Chandpur Pourasava from River Bank Erosion and Water Logging |
Project Category | : | |
Fund & Cost
Total Estimated Cost | : | 1150 |
Total Fund Released | : | 991.7 |
Percentage of Fund Released | : | 0.86 % |
Progress
Date of Financial Progress | : | 31/05/2015 |
Date of Physical Progress | : | 30/06/2015 |
Cumulative Financial Progress | : | 991.58 |
Percentage of Financial Progress Against Total Fund Released | : | 1.00 |
Percentage of Financial Progress Against Total Estimated Cost | : | 0.86 |
Percentage of Physical Progress | : | 1.00 |
Comments
Comments of Last Fields | : | |