Project Information Details

Specificaton

Project ID : 180
Project Title : Development of infrastructure to tackle climate change impacts in Muladi Pourashava, Barisal
Project Status : Completed
Project Update : প্রকল্পের অনুকূলে ৪র্থ কিস্তি বাবদ ৭৫.০০ লক্ষ টাকা ছাড় করা হয়েছে।
Number of Beneficiaries :

Dates

Approval Year : 2013-14
Project Begin Date : 01/07/2013
Date of GEO Issue : 10/10/2013
Date Trustee : 20/08/2013
Project Closing Date (Original) : 30/06/2016
Project Closing Date (Extended) : 30/06/2016

Estimated Cost

Approved Estimated Cost (TB) : 300
Approved Estimated Cost (GO) :

Meetings

Trust Meeting No : 29
PSC Meeting No :
PIC Meeting No : 1 (7/05/15)