Specificaton
Project ID | : | 42 |
Project Title | : | Installation of Solar Powered Plant at Army Headquarters and all Formation Headquarters to Mitigate Low Carbon Emission and Development of Renewable Energy (T5P4) |
Project Status | : | Completed;PCR Received |
Project Update | : | BIDS দ্বারা মূল্যায়ন করা হয়েছে। |
Number of Beneficiaries | : | |
Dates
Approval Year | : | 2010-11 |
Project Begin Date | : | 01/04/2012 |
Date of GEO Issue | : | 08/04/2012 |
Date Trustee | : | 09/02/2011 |
Project Closing Date (Original) | : | 30/04/2014 |
Project Closing Date (Extended) | : | 31/12/2015 |
Estimated Cost
Approved Estimated Cost (TB) | : | 1200 |
Approved Estimated Cost (GO) | : | 1199.9 |
Meetings
Trust Meeting No | : | 9 |
PSC Meeting No | : | 4 |
PIC Meeting No | : | |