Project ID | : | 91 |
Project Title | : | Improvement of Drainage System in Patiya Pourasava to Tackle Adverse Impacts of Climate Change |
Project Status | : | Completed;PCR Received |
Project Update | : | সমাপ্ত হয়েছে । |
Number of Beneficiaries | : | |
Dates
Approval Year | : | 2011-12 |
Project Begin Date | : | 01/07/2012 |
Date of GEO Issue | : | 03/10/2012 |
Date Trustee | : | 17/06/2012 |
Project Closing Date (Original) | : | 30/06/2013 |
Project Closing Date (Extended) | : | 31/12/2013 |
Estimated Cost
Approved Estimated Cost (TB) | : | 287.5634 |
Approved Estimated Cost (GO) | : | |
Meetings
Trust Meeting No | : | 20 |
PSC Meeting No | : | 0 |